Section 73

This is a one off fee set by Sydney Water for an application for Section 73 compliance.

The application involves composing a Design plan for the proposed development and calculation of Hydraulic Flows, Rates and Demands for Waste Water, Potable Water and Recycled Water.

After 21 days of the application being submitted, Sydney Water will then release the “Notice Of Requirements”. This is a formal document which will specify the requirements to obtain your Section 73 certification. This document may state that a Building Plan Approval, Minor Works or Major Works is required prior to the release of the Section 73 Certificate. Obtaining a Section 73 Certificate requirement will be stated in you council DA prior to Construction Certificate / Commencement

Price: $1500.00 plus. GST – APPLICATION FEE